Data Management Workshop
Brest (France)
3-4-5 Octobre 2000
Japanese
comments on the Data Management Handbook
<Procedure by Data Center>
Task JAPAN
1. Ingestion
a) Raw data source Service Argos
b) raw data format Flat ASCII
c) Unique ID assigned, ID form TBD
d) metadata added format TBD
e) Data to database TBD
2. Real-time QC
a) Tests Table 7
b) Flags Table 8
3. Data transmission
a) Format to GTS TESAC
b) Format to e-mail/ftp TBD
4. Delayed mode qc
a) Tests TBD
b) Flags Table 9
c) Format to and location of archive TBD
5. Data Validation
a) Tests TBD
6. Network
a) criteria for reseeding TBD
b) notification mechanism to PI TBD
7. Product generation
a) products Table 10
8. Data tracking
a) GTS monitoring TBD
Table 7: Real-time quality control tests in Japan
Automatic Check:
> Gross property checks
> Climatology check
> Spike and high vertical gradient check
> Vertical instability for density
> On land detection
Table 8: Japanese quality control flags
(Real-time QC flag)*
0- All check passed
1- different from climatology
2- spike, gradient
4- impossible value
8- missing value
*: Add failed test value (eg. value is 3 when "Different from
climatology" and "spike")
Table 9: Japanese quality control flags
(Delayed-mode QC flag)
0- no QC performed
2- value is good
3- value is questionable
4- value is bad
5- interpolated value
6- corrected by QC
9- missing value
Table 10. Proposed products from Japan
a) Map showing location history of floats
b) Temperature, Salinity and density profile of each float ascent.
c) Temperature, salinity and density depth-time sections
d) T-S curves of all profiles coming from a single float.
|